15 Mar 2015

Gas to Grid

IDEC has been awarded the contract from Interserve to supply, configure, test and commission a new Biogas Enrichment Control System and modification to an existing Combined Heat and Power plant control system.

The project includes for the supply and configuration of a new Allen Bradley Control Logix PLC for controlling and interfacing with packaged plant
systems used in the Biogas Enrichment process, the modification of an existing Control Logix PLC for control of the Combined Heat and Power Plant to allow operation via Biogas and Natural Gas, the configuration of an existing SCADA and the extension of the existing site wide Ethernet network.


Website design by ReZolve. An SSIDM website - v2.9.009a [2]. Loaded in 0.0273 seconds.